On 30. 4. 2024, in the presence of Minister of Transport Martin Kupka and SAGASTA CEO Jiří Čurda, construction began on the “Reconstruction of the Přibyslav – Pohled railway section,” which was designed by our company for Správa železnic (Railway Administration).
The subject of the nearly ten-kilometer construction project is the complete reconstruction of the Přibyslav and Pohled railway stations and the Přibyslav–Pohled track section. The construction includes modifications to the configuration of the railway station tracks and platforms, partial reconstruction of the station building at Pohled, and modifications to all the technology necessary for the operation of the stations and the track section. According to the schedule, construction is planned to be completed in May 2027.
The total investment cost of the construction is CZK 3 billion.